Blocks per course, courses per wall
Segmental retaining blocks stack dry on a compacted base, held by their weight and the lip or pin that locks each course back a little from the one below. The count is simple: wall length divided by the block's face length gives blocks per course; wall height divided by the face height gives courses; and the first course is buried, so add it on. Cap blocks run along the top, one per block in the top course, glued down.
blocks = (length ÷ face length) × (height ÷ face height + buried courses) × 1.05
| Block face | Per m² | 8 m wall, 600 mm + 1 buried |
|---|---|---|
| 400 × 200 mm | 12.5 | 84 blocks, 20 caps |
| 390 × 190 mm | 13.5 | 93 blocks, 21 caps |
| 300 × 150 mm | 22.2 | 142 blocks, 27 caps |
| 440 × 220 mm | 10.3 | 76 blocks, 19 caps |
The base is the wall
A block wall fails from the bottom. The base trench goes 150 mm deep and about 100 mm wider than the block on each side, and is filled with crushed rock compacted in two layers and screeded dead level, because every course above copies whatever the first one does. The first course sits half buried so the soil in front holds its toe. On soft clay the base goes deeper; on rock it can be thinner. The calculator orders the crushed rock loose with a quarter extra for compaction.
Drainage and backfill
Behind the blocks goes 300 mm of drainage gravel for the full height, with geofabric wrapped between the gravel and the soil so fines do not wash into it, and a slotted ag pipe along the base falling to an outlet or a pit. Backfill in layers and compact each one lightly, then finish with topsoil. Water that cannot drain becomes pressure, and pressure is what pushes a gravity wall over.
Height limits
Each block system publishes a maximum height for an unreinforced gravity wall, usually 600 to 900 mm on level ground with no load above. Beyond that the wall needs geogrid layers tied back into the backfill and an engineer's design, and in Victoria a building permit once it passes 1 m or sits near a boundary or a building. Anything holding up a driveway, a pool or a house is engineered regardless of height.
Worked example
An 8 m garden wall 600 mm high in 400 × 200 blocks 250 mm deep. Twenty blocks per course, three courses above ground plus one buried, 80 blocks, 84 with waste, and 21 caps. Base trench 8 m × 450 mm × 150 mm compacted: 0.68 m³ loose, about a tonne of crushed rock. Drainage gravel 8 × 0.3 × 0.8 m: 2.1 m³, about 3.2 tonnes. Nine metres of ag pipe and 13 m² of geofabric.
Common questions
How many blocks per m²?
12.5 for a 400 × 200 face, 22 for 300 × 150, 10.3 for 440 × 220.
How deep is the base?
A 150 mm trench with 100 to 150 mm of compacted crushed rock, and the first course half buried.
How high without an engineer?
Usually 600 to 900 mm, per the block system. Over 1 m needs a permit in Victoria.
Is drainage needed?
Yes: ag pipe, 300 mm of gravel and geofabric behind the wall.