A budget is the quotes, plus what the quotes leave out, plus a reserve
Most renovation budgets go wrong in the same three places. The quotes are not on the same basis, some with GST and some without, some including the fittings and some with an allowance. The costs outside the building contract are forgotten: design, engineering, the permit, appliances, window furnishings, somewhere to live. And there is no reserve for what demolition finds. This planner is a plain adding machine for your own figures that forces each of those into the open: one GST setting, a line for fees and for everything else, and a contingency that is added as a visible number.
budget = (sum of quotes and allowances) × (1 + contingency), with GST counted once
| Project | Contingency | Why |
|---|---|---|
| New extension, full drawings and engineering | 10% | Few unknowns once the footings are in |
| Kitchen or bathroom in a newer house | 10 to 15% | Plumbing and wiring behind walls |
| Whole-house renovation | 15% | Many trades, many junctions with old work |
| Period house, structural changes, restumping | 20% | Rot, asbestos, old wiring, undersized framing |
Getting quotes onto the same basis
Before adding quotes together, check four things on each. Whether it includes GST. What the allowances are, since a prime cost item of a few hundred dollars for tapware you intend to spend more on is a variation waiting to happen. What is excluded, usually in small print at the end: rubbish removal, painting, making good, asbestos, rock. And how long the price holds. A quote that is cheaper because it leaves things out is not cheaper.
Worked example
Suppose the figures you enter add up to $100,000 including GST, and the house is sixty years old, so the contingency is 20 percent. The planner shows a $20,000 reserve and a budget of $120,000, of which $10,909 is GST. If the same figures had been ex GST, the budget would be $132,000. That $12,000 gap is the size of mistake that mixing GST bases makes.
Common questions
How much contingency?
10 percent on new work, 15 on a typical renovation, 20 on an old house.
What gets forgotten?
Fees and permits, somewhere to live, appliances, window furnishings, and items chosen after the quote.
Do quotes include GST?
Quotes to homeowners must. Trade and supplier prices often do not. Check each one.
Prime cost and provisional sums?
Allowances, not prices. If the real cost is higher you pay the difference.
An adding tool for your own figures, not a price guide and not financial advice. Get written quotes, and check contract, deposit and insurance requirements in your state.