Calculators › Concrete & footings

Concrete project planner

List every pour on the job, from slabs and tank pads to footings, post holes and columns, and get one total to order. It saves as you go.

One order for the whole job

Most concrete jobs are more than one shape. A shed needs a slab and maybe a thickened edge; a fence needs a dozen post holes; a retaining wall needs a strip footing; a rainwater tank needs a round pad. Working each one out on its own is easy enough, but the decision that matters, bags or a truck, depends on the total. The planner keeps a list of pours, each with its own shape and quantity, adds them up, applies one waste allowance, and turns the result into bags, premix and weight.

total to order = sum of (volume of each pour × how many) × (1 + waste)

ShapeVolume
Rectangular slab or pathlength × width × thickness
Round slab or tank padπ × (diameter ÷ 2)² × thickness
Strip footinglength × width × depth
Round post hole or pierπ × (diameter ÷ 2)² × depth, less the post
Square pad footing or columnwidth × length × depth
Round columnπ × (diameter ÷ 2)² × height

Bags, premix, or both

A 20 kg bag of premixed concrete makes about 9.3 litres, so a cubic metre is about 108 bags and 2.2 tonnes of lifting. That is a weekend for two people. Plants supply premix in 0.2 cubic metre steps and most charge a short-load fee below about 3 cubic metres, so a small total can still favour bags. The trap with a list of pours is access: a truck can pour a slab and the footings beside it in one visit, but post holes along a back fence may need a barrow or a pump, and pours on different days are separate deliveries with separate fees.

What a builder allows We group pours by day, not by shape. Everything the truck or pump can reach in one visit goes on one order, rounded up to the next 0.2 cubic metres with a little over for the last barrow. Post holes and small pads that are set out over a few days get bags, kept dry on a pallet. And we always tell the plant what else is being poured, because a driver who knows there are three footings after the slab will wait instead of charging standby.

Worked example

A 3 × 3 m shed slab at 100 mm is 0.90 m³. Eight fence post holes, 300 mm round and 600 mm deep with a 90 mm post, are 0.04 m³ each, 0.30 m³ together. A 6 m garden wall footing, 300 × 300 mm, is 0.54 m³. The job is 1.74 m³, or 1.91 m³ with 10 percent waste: 206 bags of 20 kg, or 2.0 m³ of premix. At that size premix is the sensible order if one truck can reach all three.

Common questions

How do I work out concrete for a whole job?

Add up each pour's volume before waste, then add the waste once.

Premix or bags for several small pours?

Bags under about half a cubic metre, premix over about 3, and in between it depends on access and how many days.

How much waste should I allow?

5 to 10 percent for slabs and formed footings, more for hand-dug holes and trenches.

Can I save or share the plan?

It saves in your browser as you type. Share link and Copy totals send it to someone else.

Quantities are estimates for ordering, not structural design. Slab thickness, footing sizes and reinforcement come from your drawings or engineer. Check the yield on the bag you buy.